By Jane Steen, Head of Engagement at ETL.
This is the third and final piece from the survey we ran at Data Decoded in Manchester, where 102 data practitioners answered six questions anonymously. The first article looked at what derails projects. The second looked at how much of a project goes on simply finding out the state of the data. This article covers two other important aspects of any project: budget and decision-making.
Estimates only break in one direction
We asked how their last data project came in with regard to its budget. Of the 102 respondents: 49 said about right, 21 said over but not embarrassingly, 25 chose “let’s not talk about it” and 7 said under budget. So 45% overran and 7% came in under.
That asymmetry is an interesting finding. You might expect a set of budget estimates to miss in both directions at roughly similar rates. Some projects should come in cheaper than expected, and some more expensive. These ones don’t – under-running has very nearly disappeared as an outcome.
This suggests that maybe what’s being produced at the start of these projects isn’t really an estimate. Perhaps it’s more a number set at an acceptable level before it could be approved. A quarter of people chose “let’s not talk about it”, incidentally. If given a wry way to admit a bad overrun and a guarantee of anonymity, a quarter of respondents will take it.
Who actually chooses the tools
We also asked who chose the tools or the supplier. 45 people said they or their team decided. 17 said they provided recommendations and someone above them made a decision. 29 said it was decided above them and they were informed. 11 said that everything was already there and nobody remembers why.
So 61% had some say in the decision. It looks as though these choices aren’t being made over data practitioners’ heads.
An association with choosing the tooling
In one respect, the data does something that we didn’t expect.
Of the 45 people who chose their own tools, 14 went over budget. Of the other 57, 32 went over. It appears that teams who made the decision themselves overran at roughly half the rate of everyone else.
We ran four of these comparisons. Whether or not people spent longer on discovery made no real difference to overruns, and neither did waiting on another team. This was the only one that showed anything.
But it’s probably not about the tools
The first piece in this series found that 6% of people blamed the tooling when asked what derailed their project. So if tools rarely cause failures, better tool choices can’t be what’s saving these projects.
The shape of the result says something similar, because it isn’t a gradient. Of the teams who made the decision themselves, 31% went over budget. Of those who recommended and were overruled, 53% did. Of those who were simply told what they would be using, 59% did. Of those who inherited something nobody remembers choosing, 55% did.
In other words, being consulted and then overridden looks almost identical to never being asked. The difference is between making the decision and not making it, not between being involved and being ignored. Our interpretation, and it is an interpretation rather than a finding, is: choosing your own tools is a symptom of being close to the decisions that affect your work. Maybe this proximity is what affects the ability to stick to the budget. The tools are perhaps just the visible part of it.
One last thing on deadlines
A third of respondents – 34 people – thought that their deadline was unachievable when they first heard it. 21 of them said so frankly. But 11 of those 21 saw nothing change.
Eleven people is too few to build an argument on, which is why it didn’t get a piece of its own. But it is worth knowing that, among the people who saw trouble coming, most of them flagged it, but about half of those who raised it were ignored.
What the three articles add up to
Tooling was blamed for 6% of failures. More than half of a typical project went on establishing the state of data that the organisation already owned. And, based on this survey, the clearest thing associated with staying on budget was how close the team was to the decision.
These are organisational factors, rather than things that the purchasing department can handle. This is potentially awkward, because the budget cycle tends to be built around purchases, and the three things this survey points at – who your project is waiting on, what state your data is really in, and who gets to make decisions – don’t have a procurement process attached to them.
About the survey
102 data practitioners completed a six-question anonymous survey on our stand at Data Decoded, Manchester, on 13 and 14 October 2026. No email address or identifying detail was collected. Respondents were self-selected visitors to a single event, so this is not a representative sample of the UK market and we wouldn’t present it as one. Counts are given alongside percentages throughout so you can see the size of each group. Comparisons between groups are associations, not causes.